Pictures of construction progress

bauplatz201
Handing over the building site to the Nima Odser Sorig Foundation

In 2006 planning of the ambulance centre and winter school was not yet finished. Erecting a wall round the building site could be started, however. This wall has meanwhile been completed.

[nggallery id=2]

Building of the house was started in June 2007.

From July until September our site engineer Martin Stehr was supported by the students belonging to the project group of the RWTH Aachen.

[nggallery id=4]

Interior design was done using traditional construction methods as from September 2007.

[nggallery id=5]

The finishing touches were put on the building in October 2007 by the members of the Nima Odser Sorig Foundation.

[nggallery id=6]

In October 2007 the building was handed over to the population for use.

[nggallery id=7]

Further pictures demonstrating building progress can be seen in Susanne Weitzel ‘s weblog.